Control Layer for Partial Rescheduling

A manufacturing control layer that preserves already prepared instructions and reschedules only the affected area after disruptions.

Control Layer Frozen Instructions Postponed Instruction Urgent Order Insertion API Ready

The Problem

Traditional Scheduling

Delay / urgent order → broad rescheduling

  • Large recalculation scope
  • Already prepared shop-floor instructions may change
  • Materials, tools, and operator preparation can be disrupted
  • Manual coordination cost increases

Control Layer Approach

Delay / urgent order → Control Layer → partial rescheduling

  • Frozen instructions remain unchanged
  • Problematic instruction is postponed
  • Urgent order is inserted after the frozen range
  • Only the unfrozen area is rescheduled

Workflow Concept

[1] Production Instructions
[2] Schedule Generated
[3] Instructions Sent to Shop Floor
[4] Delay / Urgent Order
[5] Control Layer
[6] Partial Rescheduling

Demo Scenario

Example Conditions

  • Industry: Semiconductor
  • Postponed instruction: Order003 - Wafer Lot C / Material Waiting
  • Reason: Material shortage
  • Frozen range: First 2 instructions remain unchanged
  • Urgent order: UrgentOrder-X inserted after frozen range

Before Schedule

Initial production order before applying the Control Layer.

Position Instruction Line / Resource Sequence Duration
1 Order001 - Wafer Lot A / Standard Process Line 1 1 2h
2 Order002 - Wafer Lot B / Standard Process Line 1 2 2h
3 Order003 - Wafer Lot C / Material Waiting Line 1 3 3h
4 Order004 - Wafer Lot D / Standard Process Line 1 4 2h
5 Order005 - Wafer Lot E / Urgent Customer Lot Line 1 5 3h

After Applying Control Layer

Frozen

2

Postponed

1

Rescheduled

4

Unaffected

0
Position Instruction Status Reason
1 Order001 - Wafer Lot A / Standard Process Frozen Already prepared instruction remains unchanged
2 Order002 - Wafer Lot B / Standard Process Frozen Already prepared instruction remains unchanged
3 UrgentOrder-X / High Priority Urgent Inserted immediately after the frozen range
4 Order004 - Wafer Lot D / Standard Process Rescheduled Moved within the unfrozen area
5 Order005 - Wafer Lot E / Urgent Customer Lot Rescheduled Moved within the unfrozen area
6 Order003 - Wafer Lot C / Material Waiting Postponed Material shortage

What This Demonstrates

Operational Value

  • Prepared instructions are not disturbed
  • Urgent orders can be inserted without full replanning
  • Only the affected area is recalculated
  • Change boundaries are explainable to operators

Business Value

  • Reduces manual coordination after disruptions
  • Supports stable factory execution
  • Can be integrated with APS / MES systems
  • Designed as an API-ready control layer

Conceptual API Preview

This is a conceptual example. Actual API access is provided only to approved partners, customers, research collaborators, or selected evaluation users.

Example Request

{
  "industry": "semiconductor",
  "postponed_instruction": "Order003 - Wafer Lot C / Material Waiting",
  "postponed_reason": "Material shortage",
  "urgent_order": "UrgentOrder-X / High Priority",
  "frozen_count": 2
}
                    

Example Response

{
  "status": "ok",
  "control_result": {
    "frozen": [
      "Order001 - Wafer Lot A",
      "Order002 - Wafer Lot B"
    ],
    "urgent_order": "UrgentOrder-X",
    "postponed": [
      "Order003 - Wafer Lot C"
    ],
    "rescheduled": [
      "Order004 - Wafer Lot D",
      "Order005 - Wafer Lot E"
    ]
  }
}
                    

Access Policy

This demo preview is publicly viewable. Interactive access and API access are limited to selected companies, partners, universities, and qualified evaluation users.

This access policy helps prevent unauthorized usage, excessive requests, and unnecessary server load while allowing interested parties to understand the core value of the system.